Opening
sequence schedule:
In
order to ensure an organised and stress free project, we decided to create a
schedule for the pre-production and production of our opening sequence. Our
schedule is shown below.
Location
recce
- Sunday 17th November
Our
group will visit Spring Electrical and decide on the final location of our
opening sequence.
Costume
test
- Tuesday 19th November
Our
group will decide on what costume our characters would wear.
Opening
credits test
- Saturday 23rd November
Our
group will edit together a test opening credits font, helping us to establish
the font types that we will use.
Lighting
tests
- Sunday 24th November
Our
group will meet at Spring Electrical on 24th to conduct lighting tests for our
project.
Make
up tests
- Saturday 30th November
Our
group will conduct make up tests onto Joe – as he will be the hitman for our
film. This will help us establish exactly how we want the character to look
before we start filming.
Voiceover
recording
Some
time in December before filming, most likely 9th – 13th december
Our
group will guarantee to have our voiceover recording completed before filming
on the 15th, so we have a clearer vision of what the end product may look like.
Filming
- Sunday 15th December
Our
group will start our filming on the 15th of December, and attempt to get all of
our film completed before the day is over. This helps us to avoid the busy
period of late December.
Editing
- Monday 16th December – hand in date.
We
will attempt to have our film edited and completed as soon as possible, meaning
we have enough time to make improvements suggested by teacher and others.
No comments: